A Study on Construction Schedule Management Methods under Disruptive Conditions Based on Combinatorial Thinking Cover

A Study on Construction Schedule Management Methods under Disruptive Conditions Based on Combinatorial Thinking

Open Access
|Mar 2026

Figures & Tables

Figure 1:

The target response under multi-task perturbation is simulated with a scatter distribution

Figure 2:

Flowchart of schedule control using combinatorial scanning and dual-index sensitivity evaluation

Figure 3:

Construction double code arrow diagram

Analysis of duration-Cost impact on task combinations

Impact scopeIntegrated duration-Cost impact
Duration variationTaskCostCSISensitivity level (CSI)SSI [%]Sensitivity level (SSI)
10% Change (21d) (N=3)223CEH3360000.72High1.61Low
EGF4305000.78High0.51Low
226CHI2625000.46High1.89Low
BGF3990000.76High0.65Low
231DHI2100000.83High2.45Medium
AGF3885001.39High0.82Low
244EHM2205000.16Low3.85Medium
AEF3780000.29Medium1.38Low
247HIM1470000.1Low4.03Medium
BFJ3570000.28Medium1.38Low
252DHM1680000.37Medium4.52Medium
ADG3255000.62High8High
268ILM1260000.1Low13.15High
ABJ3045000.17Low9.18High
273DLM1470000.21Low13.95High
ADL2205000.27Medium16.67High

Comparative analysis between the traditional CPM and the improved model based on combinatorial thinking

Comparison dimensionTraditional critical path method (CPM)Improved model (Combinatorial thinking)
Analysis unitSingle task, single pathMulti-task combinations
Disturbance handlingNo support for disturbance simulationSimulates various combinations and disturbance scenarios
Resource & cost evaluationConsiders only time-related factorsEvaluates both schedule and cost sensitivity
Schedule adaptability under disruptionsPassive adjustment with manual interventionProactive optimization via early identification of high-sensitivity combinations

Data-driven classification criteria for cost sensitivity index (CSI)

CSI RangeInterpretationSensitivity level
CSI ≤0.222Minimal impact on cost under disturbanceLow
0. 222 < CSI < 0. 442Moderate cost sensitivityMedium
CSI ≥0.442Significant cost variation; requires interventionHigh

Process details_

Cost per unit time [CNY/day]DurationActivityProcess
450030AConstruction preparation
4000100BPavement
650030CPrefabricated beam
650028DSouth bridge platform Foundation South bridge platform Foundation
500040ENorth bridge pier foundation
70002FTransport beam
700020GSouth bridge terrace
30008HBackfill soil of the southern bridge platform
300030INorth bridge platform
500010JBackfill soil of the northern bridge platform
400015KBridge erection
200060LRoad surface
100020MCompletion of work

Analysis of the duration impact on task combinations

Impact scopeDuration impact
TaskDuration variationSchedule sensitivity index [%]Sensitivity level
Multiple tasks (N=4)10% Change (21d)(CEGF)2230.48Low
(BCGJ)2261.88Medium
(HIJK)2895.51Medium
(ADLM)29414.04High
20% Change (42d)(CBGF)2470.71Low
(DBGF)2520.8Low
(BIJK)3738.8High
(ADLM)37814.04High

Classification Criteria for Schedule Sensitivity Index (SSI)

SSI (%) RangeInterpretationSensitivity level
SSI ≤2.30Limited impact on total scheduleLow
2.30 < SSI <6.10Impact proportional to task delayMedium
SSI ≥6.10Disproportionately large impact on project durationHigh
DOI: https://doi.org/10.2478/cee-2026-0016 | Journal eISSN: 2199-6512 | Journal ISSN: 1336-5835
Language: English
Page range: 245 - 258
Submitted on: Jun 30, 2025
Accepted on: Aug 14, 2025
Published on: Mar 24, 2026
Published by: University of Žilina
In partnership with: Paradigm Publishing Services
Publication frequency: 4 issues per year

© 2026 Jingyi Chen, Zhengfeng Ma, Chen Yang, Jiangyu Xiong, Haoyun Yang, published by University of Žilina
This work is licensed under the Creative Commons Attribution 4.0 License.