Prefabrication for housing retrofit: governance, innovation and resident experience
Abstract
Prefabricated insulation elements offer a proven solution for deep renovation, yet implementation across Europe remains limited to individual pilots. This action research evaluates Estonia’s first nationwide retrofit industrialisation programme (2021–24), involving 19 owner-occupied apartment buildings (>800 dwellings). The study focused on governance and resident engagement over technical aspects. Findings indicate that the national intermediary (the Estonian Business and Innovation Agency) moved beyond grant administration to facilitate demand aggregation, supply chain qualification and price-risk management. Although an integrated renovation design and construction project delivery improved fabricator involvement, anticipated economies of scale were hindered by demand uncertainty, as apartment associations had the right to withdraw after procurement. Installation time for cladding panels was two to six weeks per building; however, the total project duration was about 14 to 44 weeks. Delays occurred in preparatory and post tasks rather than the fabrication and installation of insulation elements. While resident feedback was positive, high administrative burdens and a lack of full consensus highlight the challenges related to decision-making in non-professional building associations. The governance of the procurement process, rather than prefabrication technology alone, constitutes one primary constraint on scaling retrofit within owner-occupied housing stocks.
PRACTICE RELEVANCE
For policymakers and implementation agencies, successful industrialised retrofit depends on renovation governance and proper technical solutions. Authorities should integrate rule-setting with grant distribution to ensure administrative alignment and shift towards multi-year, demand-certain portfolios to mitigate uncertainty, disincentivising industry investment. For practitioners, collaborative involvement in early design phases is essential, with pre-design survey accuracy critical to preventing on-site problems. Agencies and practitioners should focus on standardisation of technical as well as process-related aspects, such as procurement practices and contracting methods, supporting integrated renovation design and construction delivery. Reducing organisational obstacles through standardisation and streamlined decision-making is necessary for transitioning from isolated pilots to broad industrialised retrofits.
© 2026 Ergo Pikas, Kalle Kuusk, Peep Pihelo, Roode Liias, Jürgen Pukk, Targo Kalamees, published by Ubiquity Press
This work is licensed under the Creative Commons Attribution 4.0 License.