Optimization of Construction Schedules with the Assumed Multi-Tasking of Working Brigades

Open Access
|May 2020

Abstract

The paper presents a newly developed model aimed at minimizing the downtime in working brigades work. The developed method is dedicated to the construction planned using the stream method of work organization. The model focuses on the assumption of multi-tasking of working brigades. It has been possible to model the performance depending on the type of brigade and the type of work being performed. The article also shows an example illustrating the results of the model’s operation.

DOI: https://doi.org/10.4467/2353737XCT.17.133.6884 | Journal eISSN: 2353-737X | Journal ISSN: 0011-4561
Language: English
Page range: 109 - 118
Published on: May 26, 2020
Published by: Cracow University of Technology
In partnership with: Paradigm Publishing Services
Publication frequency: 1 issue per year

© 2020 Michał Krzemiński, published by Cracow University of Technology
This work is licensed under the Creative Commons Attribution-ShareAlike 4.0 License.