Have a personal or library account? Click to login
Preliminary Analysis of Wind Parameters at the Planned Construction Sites of Wind Generators Cover

Preliminary Analysis of Wind Parameters at the Planned Construction Sites of Wind Generators

Open Access
|Mar 2024

Abstract

To choose optimal place for wind turbine, you need to know two basic parameters:

  • Vaverage – the average wind throughout the year (or during the season when more electricity is needed). The total amount of kilowatt hours of electricity you will get, depends on this parameter.

  • Vmax – the maximum possible dangerous gust of wind during a storm. The required strength depends on this parameter and hence the cost of construction.

In order to evaluate the place itself, it is possible to combine these two parameters to only one physical parameter: VBojat – the average wind speed which is devaluated by hurricanes.

In this article, it is called: “Bojatspeed”: VBojat=Vaverage3Vmax2\[{{V}_{\text{Bojat}}}=\frac{V_{\text{average}}^{3}}{V_{\max }^{2}}\].

Measurements for Vaverage must be done for at least a year, but for Vmax for at least ten years. They are obligatory before any decision about construction of wind turbine. And not generally in the country, but exactly in the particular place. A system of two devices for such measurements is described in this article: anemometer and brazmometer. Both are made in Latvia. They are purely mechanical and include no electronics – that is why they do not require battery or any service during many years.

Language: English
Page range: 90 - 105
Submitted on: Nov 24, 2020
Accepted on: Jan 8, 2024
Published on: Mar 13, 2024
Published by: Sciendo
In partnership with: Paradigm Publishing Services
Publication frequency: 4 times per year

© 2024 Vladimirs Vorohobovs, published by Sciendo
This work is licensed under the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 License.