Steam Turbine Stage Modernisation in Front of the Extraction Point Cover

Steam Turbine Stage Modernisation in Front of the Extraction Point

Open Access
|Jul 2018

Abstract

The paper presents modernisation of the steam turbine stage situated in front of the turbine extraction point, based on a 225 MW turbine LP stage as an example. The modernised design is intended to better control the steam flow in this area. In the presented design a special ring is used to drive the steam leakage flow directly to the heat exchanger. The performed experiments and numerical analyses confirmed measurable exploitation and efficiency advantages of the introduced modernisation. So far, it has been successfully applied in a number of turbines working in inland power plants, but its use can be easily extended, without need for further modification and without advantage loss, to marine turbines, especially those used as main propulsion in sea-going vessels.

DOI: https://doi.org/10.2478/pomr-2018-0062 | Journal eISSN: 2083-7429 | Journal ISSN: 1233-2585
Language: English
Page range: 116 - 122
Published on: Jul 7, 2018
Published by: Gdansk University of Technology
In partnership with: Paradigm Publishing Services
Publication frequency: 4 issues per year

© 2018 Mariusz Szymaniak, published by Gdansk University of Technology
This work is licensed under the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 License.