Have a personal or library account? Click to login

Assessment of interorganisational conflict in building refurbishment projects using EFA and PLS-SEM

By:
Open Access
|Nov 2023

Figures & Tables

Fig. 1:

SEM-PLS results for the theoretical framework describing the relation between UNC in refurbishment projects andIOC.
IOC, interorganisational conflict; PLS, partial least squares; SEM, structural equation modelling; UNC, uncertainty DF= Documentation Factor; PCF= Physical Constraints Factor; HF= Human Factor.
SEM-PLS results for the theoretical framework describing the relation between UNC in refurbishment projects andIOC. IOC, interorganisational conflict; PLS, partial least squares; SEM, structural equation modelling; UNC, uncertainty DF= Documentation Factor; PCF= Physical Constraints Factor; HF= Human Factor.

Summary of EFA_

VariablesExtracted variablesNumber of itemsEigenvaluesVariance explainedFactor loadingaCommunalitiesaCAKMO
UncertaintyDocumentation factor79.10524.98%0.574→0.7890.563→0.7760.9010.899
Physical constraints factors41.16022.24%0.635→0.7980.653→0.7170.850
Human factors71.20718.95%0.552→0.8140.597→0.7930.881
IOCInterorganisational conflict139.68774.510.784→0.9120.746→0.8280.9710.953

Analysis of the level of IOC in building refurbishment projects_

No.VariableIndicatorMean (N=188)ResultOverall meanOverall result
AConflict factorsBasic responsibilities3.13Moderately conflicting2.80Moderately conflicting
Project’s goals3.04Moderately conflicting
Task expectations3.03Moderately conflicting
Interference2.96Moderately conflicting
Standards of behaviours3.14Moderately conflicting
Final cost2.02Highly conflicting
Final duration2.13Highly conflicting
Final quality3.37Moderately conflicting
Conflict between the client and the contractor2.28Highly conflicting
Conflict between the client and the consultant3.12Moderately conflicting
Conflict between the contractor and the consultant3.22Moderately conflicting
Conflict during the design stage3.51Moderately conflicting
Conflict during the construction stage2.28Highly conflicting
Interorganisational conflict (IOC)2.80 Moderately conflicting

To what extent do you agree/disagree with the following statements relating to the refurbishment project that you have selected?

ItemStatement
1Archived document of the existing building (as-built drawings & reports) was available.12345
2Utility information of the existing building was complete.12345
3Non-destructive testing (e.g. ultrasonic testing) results were available12345
4Building inspection results were available.12345
5Building site survey results were available.12345
6The design information during the design stage was fully available.12345
7The design information during the constructing stage was fully available.12345
8Access to the site was easy.12345
9The space available for working on the refurbishment site was adequate.12345
10The space available for storing material was adequate.12345
11The site conditions (e.g. piping, electrical and structural) were foreseen12345
12The scope of work was clear.12345
13The contractual obligations were clear.12345
14Matching new materials with the existing materials was easy.12345
15The construction materials were easy to be obtained.12345
16The client’s skills and knowledge related to the refurbishment project were high.12345
17The client’s needs were certain.12345
18The changes to the design made by the client were few.12345

Uncertainty factors in building refurbishment projects_

Uncertainty factorsReference
Lack of archived documents of the existing buildingBernstein et al. (2014), Ali (2010) and Noori and Mokariantabari (2019b)
Incomplete utility information of the existing buildingBernstein et al. (2014), Volk et al. (2014) and Noori and Mokariantabari (2019b)
Unavailability of non-destructive testing resultsAli (2010) and Noori and Mokariantabari (2019b)
Unavailability of building inspection resultsDoran et al. (2009), Bulleit (2008) and Noori and Mokariantabari (2019b)
Unavailability of building site survey resultsBernstein et al. (2014) and Zolkafli et al. (2012)
Lack of design information during the design stageZolkafli et al. (2012) and Ali (2008)
Lack of design information during the construction stageAli (2014), Rahmat (2008) and Mokariantabari et al. (2019)
Difficulty in access to the construction siteTzortzopoulos et al. (2020) and Mokariantabari et al. (2019)
Inadequate space available for working on the building refurbishment siteMokariantabari et al. (2019), Noori and Mokariantabari (2019b) and Sezer (2017)
Inadequate space available for storage of materialSheth et al. (2010) and Chong and Zin (2010)
Unforeseen site conditionsKim et al. (2020) and Bernstein et al. (2014)
Unclear scope of workMokariantabari et al. (2019)
Unclear contractual obligationsManuel et al. (2016), Rahmat (2008) and Noori and Mokariantabari (2019b)
Uncertain client needsAkintan and Morledge (2013), Mustafa (2007) and Noori and Mokariantabari (2019a)
Design changes made by the clientBernstein et al. (2014) and Ofori (2013)
Lack of client’s skill and knowledge related to the building refurbishment projectVaux and Kirk (2014) and Ali and Au-Yong (2021)
Difficulty in matching new materials with existing materialsVaysburd et al. (2014) and Noori and Mokariantabari (2019b)
Difficulty in obtaining construction materialsAziz and Abdel-Hakam (2016) and Diab and Mehany (2021)

Initial assumptions of EFA_

VariablesKMOBTS
Approx. chi-squaredfSignificance
Uncertainty0.8992,490.6061530.000
IOC0.9532,874.404780.000

Analysis of the level of uncertainty in refurbishment projects_

No.VariableIndicatorMean (N=188)ResultOverall meanRankOverall result
ADocumentation factorArchived document2.62Moderately uncertain2.502Moderately uncertain
Utility information2.56Moderately uncertain
Non-destructive testing1.73Highly uncertain
Building inspection2.64Moderately uncertain
Building site survey2.76Moderately uncertain
Design information during the design stage2.58Moderately uncertain
Design information during the constructing stage2.65Moderately uncertain
BPhysical constraints factorAccess to the site2.20Highly uncertain2.311Highly uncertain
Space for working2.48Moderately uncertain
Space for storage of material2.23Highly uncertain
Unforeseen site conditions2.34Moderately uncertain
CHuman factorScope of work2.27Highly uncertain
Contractual obligations2.27Highly uncertain2.623Moderately uncertain
Matching of new materials3.03Moderately uncertain
Obtaining construction materials2.53Moderately uncertain
Client’s skill and knowledge2.84Moderately uncertain
Client’s needs2.45Moderately uncertain
Design changes made by client2.97Moderately uncertain
Uncertainty in refurbishment projects 2.48 Moderately uncertain

Path coefficient of the relationship between uncertainty and IOC in refurbishment projects_

PathBt-valueR2Q2P-value
UNC → IOC0.4354.985**0.2810.271P < 0.01

Interorganisational conflict factors in building refurbishment projects_

Interorganisational conflict factorsReferences
Disagreement over basic responsibilitiesNoori et al. (2021) and Narh et al. (2015)
Disagreement on how to achieve the project’s goalsAli et al. (2014), Kerzner (2013) and Harmon (2003a, 2003b)
Disagreement over task expectationsYou et al. (2018) and Vaux and Kirk (2014)
Disagreement over the interference of other project members in their worksCao et al. (2020), Bekele (2015) and Moura and Teixeira (2010)
Disagreement over ethical standards of behaviourNoori et al. (2021), Lumineau et al. (2015) and Kang (2004)
Disagreement over the final cost, duration and qualityAnsari et al. (2022), Khahro and Ali (2014) and Noori et al. (2021)

To what extent did the following interorganisational conflicts occur in the refurbishment project?

ItemInterorganisational conflicts
1The organisations involved in the refurbishment project agreed on their basic responsibilities.12345
2The organisations involved in the refurbishment project agreed on achieving the project’s goals.12345
3The organisations involved in the refurbishment project agreed on task expectations.12345
4The organisations involved in the refurbishment project agreed on the interference of other project members in their works.12345
5The organisations involved in the refurbishment project agreed on standards of behaviour.12345
6The client and the contractor agreed on the final cost of the refurbishment project.12345
7The client and the contractor agreed on the final duration of the refurbishment project.12345
8The client and the contractor agreed on the final quality of the refurbishment project.12345
9The level of organisational conflict between the client and the contractor in the refurbishment project was low.12345
10The level of organisational conflict between the client and the consultants in the refurbishment project was low.12345
11The level of organisational conflict between the contractor and the consultants in the refurbishment project was low.12345
12The level of interorganisational conflict during the design stage of the refurbishment project was low.12345
13The level of interorganisational conflict during the construction stage of the refurbishment project was low.12345
DOI: https://doi.org/10.2478/otmcj-2023-0013 | Journal eISSN: 1847-6228 | Journal ISSN: 1847-5450
Language: English
Page range: 178 - 191
Submitted on: Jan 28, 2022
Accepted on: Jul 16, 2023
Published on: Nov 25, 2023
Published by: University of Zagreb
In partnership with: Paradigm Publishing Services
Publication frequency: 1 issue per year

© 2023 Adel Noori, published by University of Zagreb
This work is licensed under the Creative Commons Attribution 4.0 License.