Cost and time performance of traditional-, direct labour- and management-procured public projects in Ondo State, Nigeria
 Cover

Cost and time performance of traditional-, direct labour- and management-procured public projects in Ondo State, Nigeria

Open Access
|Dec 2017

Figures & Tables

Tab. 1

Factors influencing the choice of procurement method used in public project delivery

FactorsMin.Agen.LG.Tert.OverallANOVA
MISRkMISRkMISRkMISRkMISRkFSig.
Price competition - need to achieve value for money and public accountability4.2713.7543.4024.2713.9811.6220.199
Speed - in all phases of the project4.1323.50103.6014.0023.8620.6540.585
Time certainty - ability to complete project within the agreed duration4.0743.8633.1074.0023.7931.8690.151
Complexity of the project4.1323.6373.2063.9143.7742.0710.119
Flexibility - ability to accommodate changes during design and construction phases3.8674.0013.2253.6483.6951.3430.275
Quality - the need to fulfil client’s expectation of essential project characteristics3.9363.7163.1073.7363.6461.8090.162
Familiarity - based on previous experience3.8083.43123.3333.7363.6270.5610.644
Simplicity - in terms of activities, process and procedure4.0743.5793.1073.36123.5882.4300.080
Price certainty - the ability to keep expenditure within budgeted estimate3.8083.50102.90103.9143.5791.8220.159
Government policy - on using a particular procurement route3.60103.6372.90103.6483.45101.3660.267
Dispute resolution and arbitration3.36124.0013.3332.91133.34112.4060.083
Responsibility - the need to be involved in and to be kept informed about the project through its life3.40113.7552.80133.40113.33121.1050.359
Risk allocation - knowledge on how and to what degree uncertainties/risks have been passed to or shared among parties3.33133.14132.90103.44103.22130.9060.448

[i] Note: Min. = ministries; Agen. = agencies; LG. = local governments, Tert. = tertiary institutions; ANOVA = analysis of variance; Rk. = rank; Sig. = significance.

Tab. 2

Cost and time analysis for traditionally procured public projects

S/nProject typeFC. (mill.)IC. (mill.)Dev.% Dev.FT. (weeks)IT. (weeks)Dev.% Dev.
1Educational building45.039.06.015.445301550.0
2Educational building18.011.56.556.52824416.7
3Social building600.0600.00.00.096762026.3
4Residential116.093.023.024.746361027.8
5Residential2.32.30.00.0101000.0
6Residential5.75.70.00.0121200.0
7Residential5.65.60.00.0151500.0
8Offices37.533.04.513.63430413.3
9Educational building501.3395.5105.726.748351337.1
10Educational building150.0150.00.00.072522038.5
11Residential13.513.50.00.0321517113.3
12Offices55.450.74.79.336241250.0
Average12.512.21031.1

[i] Note: FC. = final cost; IC. = initial cost; Dev. = deviation; FT. = final time; IT. = initial time; mill. = million; exchange rate: 1 Euro = 419.6 Naira (2017).

Tab. 3

Cost and time analysis for direct labour-procured public projects

S/nProject typeFC. (mill.)IC. (mill.)Dev.% Dev.FT. (weeks)IT. (weeks)Dev.% Dev.
1Offices56.046.010.021.73224833.3
2Educational building4.54.50.00.04400.0
3Social building (ren.)1.51.00.550.04400.0
4Utility building4.54.50.00.06600.0
5Health care centre6.05.01.020.032201260.0
6Health care centre5.05.00.00.064250.0
7Educational building7.17.10.00.054125.0
8Social building (ren.)10.510.00.55.03224833.3
9Offices830.0830.00.00.03224833.3
10Social building (ren.)10.08.51.517.62824416.7
11Residential28.230.0−1.8−6.01718−1−5.6
12Educational building4.44.5−0.1−2.264250.0
Average1.08.8424.7

[i] Note: FC. = final cost; IC. = initial cost; Dev. = deviation; FT. = final time; IT. = initial time; mill. = million; ren. = renovation; exchange rate: 1 Euro = 419.6 Naira (2017).

Tab. 4

Cost and time analysis for management-procured public projects

S/nProject typeFC. (mill.)IC. (mill.)Dev.% Dev.FT. (weeks)IT. (weeks)Dev.% Dev.
1Educational building67.063.04.06.3726757.5
2Social building3,213.01,883.01.370.66600.0
3Educational building29.629.60.00.0242400.0
4Educational building110.0110.00.00.032201260.0
5Social building69.469.40.00.053302376.7
6Social building121.1121.10.00.03021942.9
7Health centre250.0217.033.015.232211152.4
8Health centre172.7160.212.47.83224833.3
9Educational building158.5158.498.20.11145262119.2
10Social building54.051.12.95.7242400.0
11Residential69.769.70.00.0422022110.0
12Residential245.0245.00.00.040241666.7
Average115.28.81447.4

[i] Note: FC. = final cost; IC. = initial cost; Dev. = deviation; FT. = final time; IT. = initial time; mill. = million; exchange rate: 1 Euro = 419.6 Naira (2017).

Tab. 5

Summary of the cost performance of public building projects, analyzed using the paired-samples t-test

Procurement typeOverall deviation (million)Overall % deviationStd. deviationStd. error meanTDfSig. (two-tailed)
Traditional12.512.230.18.71.44110.177
Direct labour1.08.82.90.91.13110.281
Management procurement115.28.8382.6110.51.04110.319

[i] Note: Std. = standard; Df = degrees-of-freedom; Sig. = significance; exchange rate: 1 Euro = 419.6 Naira (2017).

Tab. 6

Summary of the time performance of public building projects using the paired-samples t-test

Procurement typeOverall deviationOverall % deviationStd. deviationStd. error meanTDfSig. (two-tailed)
Traditional1031.1824.296110.001**
Direct labour424.7412.974110.013**
Management procurement1447.41752.845110.016**

Note: Std. = standard; Df = degrees-of-freedom; Sig. = significance;

** significant at p<0.05; exchange rate: 1 Euro = 419.6 Naira (2017).

DOI: https://doi.org/10.1515/otmcj-2016-0022 | Journal eISSN: 1847-6228 | Journal ISSN: 1847-5450
Language: English
Page range: 1593 - 1603
Submitted on: Sep 1, 2017
Accepted on: Nov 14, 2017
Published on: Dec 29, 2017
Published by: University of Zagreb
In partnership with: Paradigm Publishing Services
Publication frequency: 1 issue per year

© 2017 Douglas Omoregie Aghimien, Olufemi Osanyinro, Taiwo Fadeke Adegbembo, published by University of Zagreb
This work is licensed under the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 License.